The company is proud of its history.
 02.09                                    2024
                            
                                                                    02.09                                    2024
                                                            
                        
                        JSC Trust Shakhtospetsstroy, as a property complex, was taken over by the Republic of Belarus and assigned the right of economic management to the Republican Unitary Enterprise «Shakhtostroy».
 16.12                                    2021
                            
                                                                    16.12                                    2021
                                                            
                        
                        
	On December 16, 2021, at the Petrikovsky GOK mine, combine harvesters from GKU-2 GKU of JSC Trest Shakhtospetsstroy (head – A.S. Sevruk) delivered one millionth ton of ore from mining and preparatory workings and service chambers.
 
	 Since the beginning of the construction of the Petrikovsky GOK facility, employees of the Trest Shakhtospetsstroy State Enterprise have installed 35 conveyors with a total length of 11 km, laid more than 80 km of power cables and more than 140 km of control and communication cables through mining workings.
 27.08                                    2021
                            
                                                                    27.08                                    2021
                                                            
                        
                        
	On August 27, 2021, the Petrikovsky GOK was officially commissioned.
	 President of the Republic of Belarus Alexander Grigoryevich Lukashenko personally took part in the commissioning ceremony of the Petrikovsky mining and processing complex of Belaruskali. The Head of State carried out the symbolic launch of the enterprise by pressing the start button of the mining combine on the control panel. The process of operation of the equipment was demonstrated to the participants of the event online.
 
	 JSC Trest Shakhtospetsstroy is the general contractor for the construction of the Petrikovsky mining and processing complex. Thanks to the well-coordinated joint work of the labor collectives of Belaruskali OJSC and Trest Shakhtospetsstroy OJSC, the sinking of the 1st and 2nd shafts of the Petrikovsky GOK was completed in April 2019. Currently, preparatory work has been completed at the mine's industrial site and work is underway on the construction of facilities of the third stage of construction.
 
	 The Petrikovsky GOK is scheduled to reach its design capacity in early 2022. The design capacity of the Petrikovsky GOK reaches 1.5 million tons of potassium chloride per year.
 11.12                                    2020
                            
                                                                    11.12                                    2020
                                                            
                        
                        This is one of the most important stages in the construction of new mines. The cage shaft carries people and equipment to the mine, and the mine begins to develop its underground infrastructure.
The resources of the Darasinsky mining and processing plant will extend the service life of the PU-3 of Belaruskali for at least 50 years. The project capacity of the plant will be about 8 million tons of ore per year, with a subsequent increase to 9 million.
 30.07                                    2020
                            
                                                                    30.07                                    2020
                                                            
                        
                        At 2 a.m., 30.07.2020 Mining and capital unit №3 of the MCD (ПКС-8 №46) finished the boring of the research working, which crossed the II Potash horizon of PU-5! The thickness of the silvinite layer at the autopsy site was respectively: 1 silvinite layer – 0.95 meters; 2 silvinite layer − 0.73 meters; 3 silvinite layer − 0.60 meters.
The opening of the II Potash horizon opens up additional opportunities for ore mining at the PU-5.
 May 2019
                            
                                                                    May 2019
                                                            
                        
                        In May, the Darasinsky mining and processing plant construction was started. The mine field of the Darasinsky mining and processing plant will be located under the territories of Soligorsk, Lyuban and Slutsk districts. The new mine will become the raw material base for PU-3 and extend its service life by at least 50 years.
 April 2019
                            
                                                                    April 2019
                                                            
                        
                        Thanks to the well-coordinated joint work of JSC «Belaruskali» and JSC «Trest Shahtospecstroy», the sinking of the first and second shafts at the Petrikovsky mining and processing plant was completed in April 2019. It is planned to attain the project capacity in 2021.
 12.08                                    2018
                            
                                                                    12.08                                    2018
                                                            
                        
                        On August 12, 2018 the mining and capital section №2 reached the productive layers of the 4th potash horizon by an exploratory transport raise at PU-2, which was the first time in the history of Belaruskali.
 31.03                                    2017
                            
                                                                    31.03                                    2017
                                                            
                        
                        On March 31, 2017 the President of the Republic of Belarus Alexander Lukashenko and the President of Turkmenistan Gurbanguly Berdimuhamedov cut the ribbon and pressed the symbolic start button.
 November 2017
                            
                                                                    November 2017
                                                            
                        
                        In August, 2017 the shaft-sinking section №1 team of the shaft-sinking department achieved a monthly rate of 80 passage metres in shaft-sinking at the Petrikovsky mining and processing plant, breaking its own shaft-sinking record at the Beryozovsky PU.
In November, 2017 a new record was achieved by the shaft-sinking section №2 of the shaft-sinking department. A monthly rate in shaft-sinking with the construction of advanced concrete support reached 80,8 passage meters.
 09.05                                    2016
                            
                                                                    09.05                                    2016
                                                            
                        
                        On May 9, 2016 the vertical shaft №1 started to be sunk at Petrikov field, and the first tons of rock were delivered on top.
 August 2016
                            
                                                                    August 2016
                                                            
                        
                        On August 18,2016 at the depth of 295 meters, in the chamber at the cell shaft and the productive potash reservoir junction the piecemeal descent and assembly of the tunnel boring machine (CRS-3) were completed in a record time.
On the night of August 29-30 the cross connection between the cage and skip shafts was successfully completed. The tunnel boring machine CRS-3 №1 moved into the junction chamber of shaft №1 with a pinpoint accuracy.
 20.02                                    2015
                            
                                                                    20.02                                    2015
                                                            
                        
                        On February 20, 2015 Denis Diulin was appointed Chief Executive Officer of JSC «Trest Shahtospecstroy».
 23.10                                    2012
                            
                                                                    23.10                                    2012
                                                            
                        
                        In October, thanks to the JSC «Belaruskali» and JSC «Trest Shahtospecstroy» mine surveyors calculations the cross connection between the horizontal minefield workings and the vertical mine shaft was completed. In the night of October 22-23, 2012 after passing a winding path underground along the survey marks, the tunnel boring machine №8 moved into the shaft №5 with a pinpoint accuracy. This date became one of the most significant events in the Beryozovsky PU history.
 May-June 2011
                            
                                                                    May-June 2011
                                                            
                        
                        The shaft-sinking department completed two shafts (№5 and №6) of the Beryozovsky PU in a short time frame. The skip shaft sinking has been completed in June, 2011 at a depth of 665 metres, the cage shaft sinking – on May 1, 2011 at a depth of 600,56 metres. In August, 2010 the record rate of 61,6 metres per month in skip shaft-sinking was achieved by the shaft-sinking section №1.
 2010
                            
                                                                    2010
                                                            
                        
                        In 2010, a turn-key construction contract was signed by the General contractor represented by JSC «Belgorhimprom» and by the State concern «Turkmenhimiya». The construction project value was estimated at $1 billion.
 08.05                                    2009
                            
                                                                    08.05                                    2009
                                                            
                        
                        On May 8, 2009 the first stage of the construction project of the Krasnoslobodsky PU was commissioned. The first stage of the project commissioning was accepted by the President of the Republic of Belarus A.Lukashenko.
The team of JSC «Trest Shahtospecstroy» completed approximately 40% of the total building and assembly works of this project: shafts №1 and №2, pitbottoms, temporary buildings and structures associated with shaft-sinking, 1,5 km of conveyor gallery path construction project.
The Krasnoslobodsky Production Unit (PU-5) of Belaruskali construction project was completed in record-breaking time by world standards.
 2008
                            
                                                                    2008
                                                            
                        
                        In 2008, a new speed record of 57 meters per month in shaft-sinking was achieved in the skip shaft, in the cage shaft – 47 meters per month.
With the increased volume of work and expansion of the construction projects the repair,construction and erection department was divided into a repair,construction and erection department №1 and a repair,construction and erection department №2, they carried out three activities: construction, installation and major repairs.
In December 2008, the mining and capital department was founded.
 2006-2007
                            
                                                                    2006-2007
                                                            
                        
                        In August 2006, V.Startsev was elected Chairman of the Supervisory Board. Nikolay Skripnik was appointed Chief Executive Officer.
On November 1, 2007 Sergey Garbatsevich was appointed Chief Executive Officer of JSC «Trest Shahtospecstroy».
 01.02                                    2004
                            
                                                                    01.02                                    2004
                                                            
                        
                        In February 2004, a shaft-sinking department was founded for the purpose of shaft-sinking and construction of the mining part of the Krasnoslobodsky PU.
In February 2005, miners began sinking the second shaft of the Krasnoslobodsky PU, in April – the first. The work was carried out by freezing method, guided by the fact that the first 230 meters in depth were composed of watered sands. A speed record of 33 meters per month in shaft-sinking was achieved in frozen rocks.
 14.02                                    2003
                            
                                                                    14.02                                    2003
                                                            
                        
                        On February 14, 2003 to replenish the crude-ore resources of PU-2, the construction of the Krasnoslobodsky PU was officially opened.
 04.05                                    2000
                            
                                                                    04.05                                    2000
                                                            
                        
                        On April 12, 2000 the agreement on transformation of the employee-owned (public) enterprise Trust «Shahtospecstroy» into JSC «Trest Shahtospecstroy» was signed and the decision on issue of the shares was made.
On May 4, 2000 JSC «Trest Shahtospecstroy» was founded.
 01.03                                    1996
                            
                                                                    01.03                                    1996
                                                            
                        
                        On March 1, 1996 the subsidiary production unit enterprise «ROMSOL» was founded. Its main activities were production of metal constructions and non-standardized facilities of any complexity for construction works, as well as the provision of a wide range of services for metalworking and design of metal structures.
 1993-1995
                            
                                                                    1993-1995
                                                            
                        
                        At PU-1, shaft-sinking, erection and exploratory mining works between the 2nd and the 3rd horizons were completed to increase the capacity by 500 thousand tons of rock salt per year.
At PU-2 the ore-dressing plant was reconstructed in connection with the transfer to the new GOST; reconstruction of sump cleaning and join workings of shaft №1 was completed; the mechanical workshop and garages for interfactory traffic were built.
At PU-3 the ore-dressing plant (the 9th technological line) was reconstructed.
 19.02                                    1992
                            
                                                                    19.02                                    1992
                                                            
                        
                        In January, 1990 the Trust «Shahtospecstroy» was found on the basis of the Soligorsk and Kirovsk mine construction departments. The Trust «Shahtospecstroy» included the Soligorsk and Kirovsk mine construction departments, a repair-construction and erection department and the service facilities.
On December 30, 1991 the state property purchase agreement was signed. The Trust «Shahtospecstroy» was one of the first in Belarus to be privatized.
On February 19, 1992 the employee-owned (public) enterprise Trust «Shahtospecstroy» was registered.
 01.02                                    1989
                            
                                                                    01.02                                    1989
                                                            
                        
                        On February 1, 1989 by Order of the Minister of the production of mineral fertilizers N.Olshansky, the Kirovsk mine construction department and the Soligorsk mine construction department merged.
At the age of 56, the first head of the Soligorsk mine construction department A.Pivovarov left for a preferential miner’s retirement pension. Valery Startsev was appointed head of the Soligorsk mine construction department.
 1977-1987
                            
                                                                    1977-1987
                                                            
                        
                        During the first 10 years of operation from 1977 to 1987, a total of about 200km of mine workings was completed at Belaruskali mines. More than 1 million m3 of rock mass was broken down and brought to grass, large volumes of concrete and salt concrete were placed, and several thousand sets of reinforced concrete and screw roof bolting were installed.
The Soligorsk mine construction department put into operation launch complexes to increase the capacity of the annual production of mineral fertilizers at Belaruskali Production Units (PUs):
− by 208 thousand tons – at PU-1;
− by 40 thousand tons – at PU-2;
− by 100 thousand tons – at PU-3;
− by 208 thousand tons – at PU-4.
Also, the start-up facilities of shaft №4 constructions at PU-1 and PU-2 were put into operation, and the ore-dressing plants were reconstructed in connection with a transfer to the new GOST.
 15.02                                    1977
                            
                                                                    15.02                                    1977
                                                            
                        
                         09.12                                    1976
                            
                                                                    09.12                                    1976
                                                            
                        
                        For the purpose of timely implementation of mining capital and mining development works to ensure the commissioning of potash production capacities at Soligorsk Production Unit №4, the Minister of chemical industry of the USSR L.Kostandov issued an order on the Soligorsk mine construction department foundation.
 
                         
                 
                